top of page

Belinder Pump Station Improvements

Project Update - September 14, 2026

You may notice increased activity beginning the week of September 14 and lasting for approximately 4-5 weeks. During this time, the contractor will begin excavation for a new electrical duct bank that will feed the new electrical building located in the front yard. In addition, they will begin excavation for the new generator pad in the backyard.

2026-09-14 Belinder Graphic

Upcoming Construction Activities

Site Work & PS Exterior Work (August-January)

  • Excavation and installation of new electrical duct bank

  • Installation of new generator pad and generator

  • Install exterior concrete steps, stoops, and miscellaneous equipment pads

  • Demo exterior HVAC equipment and install new equipment pad

PEFTF Modifications (November-January)

  • Clean PEFTF and demo remaining equipment inside

  • Install PEFTF PRV’s

  • PEFTF concrete repairs and installation of aluminum plating

Pump Station Structural Upgrades (August-November)

  • Install new stairs and handrail

  • Install footings for garage expansion

  • Install new building/garage addition floors

  • Install equipment pads

  • Install new structural beams, grating, and handrail

  • Install new floor access manholes and hatches

Pump Station Architectural & MEP Upgrades (August-January)

  • Install temporary building and equipment protection

  • Install CMU masonry and insulation for new additions

  • Demo existing pump station shell (masonry, roof, finishes, etc.)

  • Install structural steel for building and garage expansion

  • Install new CMU masonry and insulation for main pump station

  • Install trusses, roof, brick, windows, and doors

  • Setup bypass for electrical gear switchover

  • Install new electrical gear and execute switchover

Chemical Tanks & Systems (November-February)

  • Setup temporary chemical system

  • Demo existing chemical tanks and pumps

  • Installing new chemical tanks and pumps

Dry Weather Pumps, Piping, & Appurtenances (October-January)

  • Modify existing flow metering vault for bypass pumping

  • Relocate existing dry weather flood pump piping

Wet Weather Pumps, Piping, & Appurtenances (November-January)

  • Setup bypass pumping

  • Demo existing wet weather pumps and piping

  • Install new wet weather pumps and piping

  • Demo existing PEFTF and wet well drain pumps

  • Install new PEFTF and wet well drain pumps

Safety Reminder

For the safety of the public and construction crews, please observe all posted signage, avoid entering active work zones, and use caution when traveling near construction activity.

More Information

We appreciate your patience and cooperation during this period of construction. If you have any questions or require additional information, please contact the project team at info@jcwprogram.com,

 

Note: All dates and work sequences are subject to weather conditions and field constraints. Activities may shift as needed to maintain project progress. Residents may notice increased construction traffic, equipment activity, and intermittent noise during work hours. JCW and the project team will work to minimize disruptions where possible.

Sign up for Belinder Pump Station project email notifications and updates.


If you want to receive project updates and notification emails when major changes are happening at the Belinder Pump Station Improvements site, complete the attached form and submit.

Your email will only be used for notifications about Belinder. You can opt out at any time.  If you want notifications about other JCW projects, visit: https://www.jcwprogram.com/connect 

first name

last Name

email address

If you detect odors we would like to know so we can address them.  You can fill out an odor complaint form by clicking on the “Odor Complaint Form” button. This form notifies Operations & Maintenance staff and top leadership directly. 

Belinder Pump Station

 Existing Belinder Pump Station prior to upgrade 

Project

The Belinder Pump Station facility is located at 5700 Belinder Road, at the intersection of State Park Road and Belinder Road, and both the Kansas City and Mission Hills Country Clubs. 

 

Typical sanitary sewer flow generated by communities in the lower portion of the Brush and Rock Creek basins flows by gravity sewers to the pump station, which then pumps it northwest to the Nelson Wastewater Treatment Facility located near the I-35 and Lamar interchange.  

 

During heavy rain events, storm water enters the sewer system through old sewers, manholes, and connections on private property (homes and businesses) and can exceed the capacity of the dry weather pump station.  There is a separate wet weather pump station and Peak Excess Flow Treatment Facility (PEFTF) at this location that treats and disinfects the excess wet weather flow before its release to Brush Creek.    

 

This project will replace and improve aging equipment at the facility. Because the facility was constructed in the late 1940’s, these improvements will require building expansion to house new equipment and meet current building codes. Regulatory requirements involve the use of additional chemicals to protect the safety of Brush Creek. 

​Project Drivers and Benefits

JCW is replacing and improving aging equipment to extend the life of the facility, increase reliability, and improve facility operations while trying to maintain the aesthetics of the facility and be a good neighbor. 

There is a regulatory requirement from the Kansas Department of Health and Environment (KDHE) to improve the chemical treatment system for wet weather discharges.

Project Schedule

The project is in design in 2024. Construction is scheduled to begin in late 2025 and be completed by early 2028.  This page will be updated with more details as the project progresses.

​​​Engagement

Belinder Pump Station Location: 5700 Belinder Road

Belinder Pump Station Location: 5700 Belinder Road

Sign Up for 
Notifications

​Keep checking back, as information is updated it will be posted on this website. You can also sign up for notifications. 

presented

Informational Meeting -  September 11, 2024
MATERIALS PRESENTED

Board 1 - What does this facility do? 

Belinder Pump Station was built in 1947, and is one of eight pump stations that sends flows to the Nelson Wastewater Treatment Complex.  It’s located at the corner of State Park Road and Belinder Avenue. The pump station consists of a dry weather and wet weather pump station. The dry weather pump station conveys up to 10.6 million gallons per day of raw wastewater to Nelson Wastewater Treatment Facility in Mission, KS.  During large storm events, storm water infiltration can overwhelm the collection system and exceed the dry weather pump station capacity. The excess flow is temporarily stored in the below ground Peak Excess Flow Treatment Facility (PEFTF) until the storm passes and the pump station returns to normal operating conditions. If the PEFTF capacity is exceeded, flow is released into Brush Creek after treatment which includes screening, settling, and chemical disinfection. 

Belinder Pump Station - What does this facility do?

Board 2 - Project Drivers 

There are three main drivers associated with this project: replacement of aging equipment, improving water quality, and implementing JCW’s long-term plan.  Equipment reaching the end of its life will need to be replaced to maintain continued service, increase reliability and safety, and update the facility to meet current codes.  Currently JCW adds chlorine for disinfection of the PEFTF flow to Brush Creek during large storm events.  To improve water quality, sodium bisulfite will be added to remove the residual chlorine which can be toxic to aquatic life. This is a process called dechlorination.  This project is part of JCW’s 25-year Integrated Plan approved by the Kansas Department of Health and Environment (KDHE) and has a target completion date of 2028.  

Belinder Pump Station - Project Drivers

Board 3 - Street Level View 

The renderings on the left show the existing facility and, on the right, the proposed facility.  These improvements will require a facility expansion on the front of the property towards the southwest and southeast for our new electrical, dumpster, and chemical rooms.  The goal of the design is for the architecture to serve as a good neighbor to the adjacent property owners and appear as another residence within the neighborhood.  The architectural style of the expansion will match the colonial cottage style of the existing building with shingle pitched roof, colonial pediment and surround at the entrance door, white trim divided windows with shutters, and use of white cornice/fascia on tumbled red blend brick walls. The existing brick screening wall in front of the station conflicts with the expansion and will be removed.  The majority of equipment and hatches behind the wall will be removed or knocked down flush with the ground level so as not to be seen. The renderings are not final design and were created at 30% of final design. Slight changes may result as the design team progresses through final design.  Landscaping is shown in concept only.

Belinder Pump Station - Street Level Views of facility before and after.

Board 4 - Site Plan 

There are several site improvements to the property.  The existing driveway will be expanded for easier truck access off State Park Road and Belinder Avenue (darker grey).  The existing building will expand towards State Park Road and to the southeast (blue). The expansion facing State Park Road will be for a new dumpster/washer compactor room. This will collect the larger debris in the water that is removed from the new mechanically operated bar screens. The facility expansion on the front, or southeast, of the property will house the new electrical and sodium bisulfite rooms.  A new electrical room will help meet current code requirements and provide better phasing of construction to maintain operations.  The generator and HVAC equipment will be replacing existing (purple).  A new chemical addition point will be added to the below ground PEFTF for the dechlorination process (light green).

Belinder Pump Station - Site Plan

Board 5 - What to Expect During Construction 

On projects with a significant impact within a community we typically receive questions related to the following topics: noise, traffic, odor, lighting, and dirt.  These topics with mitigation efforts for this project are provided on the board.  Some additional anticipated items to expect during construction are temporary pumping, construction trailer, and heavy equipment (i.e., cranes, forklifts, etc.). Sound attenuation will be provided on the temporary bypass pumps as these may be required for a few months during construction.  

Belinder Pump Station - What to ExpectDuring Construction

Board 6 - Landscaping and Lighting Plan 

Belinder Pump Station operates 24/7 and some lighting is required for safety and security. Existing exterior light fixtures will be replaced along with at least two new lights.  Facility lighting will be in accordance with the City of Fairway Municipal Code. All exterior fixtures will be down cast and will be warm lighting. Due to the building expansion and lack of contractor staging onsite the three trees on the east of the property will be removed for access and construction.  New trees will be planted in the area shown on the board.   Additional landscaping will be provided in front of the building and around the access point near the west driveway to enhance curb appeal.   

Belinder Pump Station - Landscaping and Lighting Plan

Board 7 - Additional Information 

A public open house was held on September 11th to inform the public of the project and the City of Fairway’s Planning Commission will review JCW’s planning application in a public meeting on October 28, 2024.  This project is currently in design and will reach its 60% milestone in November.  100% design is expected by April 2025 with bidding through the summer.  The contractor is expected to mobilize and start construction in the fall of 2025.  Construction is estimated to be 28 months with completion in 2028 and an estimated total project cost of $22-25 million. 

You can sign-up for email notifications about the project at jcwprogram.com/belinder or scan the QR code for more information. 

Frequently Asked Questions

bottom of page