top of page

Project Notice - updated May 21, 2025:

  • There will be construction equipment near I-435 and State Line Road throughout May.

  • Intermittent lane closures in State Line Way, near 104th Street are expected throughout May.

  • Temporary Trail Closure:

    • A new sewer force main pipe is being installed across/under Indian Creek (near the Indian Creek Trail south of Indian Creek, at State Line Rd and I-435) and will continue for approximately 2 to 3 weeks. 

    • A temporary trail, paved with gravel has been put in place for access. However, it may be closed at any time to restore the concrete paving or other needs by the construction team. Please follow all safety and signage notices. Weather permitting, the trail is scheduled to reopen permanently by June 13.​

    • We apologize for the inconvenience.  We are fully aware that the trail does not have a good alternative safe route for detouring and will make every effort to move as quickly as possible to get the construction work done safely and the trail restored.

  • We appreciate your patience as we work to safely complete the project. For the safety of the public and our workers, please follow all signage and safety guidelines.

Project-Purpose

Project Purpose:

The purpose of the State Line Road Pump Stations and Forcemain project is to capture flows from the Leawood Service Area that currently drain across the State Line into the Kansas City, Missouri (KCMO) collection system and send that flow to JCW’s newly completed Tomahawk Wastewater Treatment Facility.

 

JCW evaluated the business case for this project and determined that the project will save JCW over $100 Million over 20 years, compared to the cost of continued treatment of all flows by KCMO. Along with these long-term savings, this project will pay for itself in approximately 6 to 7 years, providing near term financial benefits to the residents of Johnson County.

Proposed State Line pump stations and forcemain locations

Map shows the general locations of proposed State Line pump stations and forcemain.

Sub-Basin Boundaries

Map above shows the sub-basin boundaries and how the gravity flow of the sewers is directed to the sites.

Project-Schedule

Project Schedule:

State Line Pump Stations and Forcemain Project Design Schedule

  • 30% Design – Completed Spring 2023

  • 60% Design – Completed Fall 2023

  • Public Open House or Public Meeting prior to application for Final Development Plan – Completed

  • 95% Design – Completed Winter 2024

  • Bidding of Projects – Completed Fall 2024

  • Notice to Proceed for Construction and Construction Start – Winter 2025
    NOTE:  JCW will update this web page and provide more details on construction schedules and road impacts after construction is authorized and a detailed schedule is developed.

​October 31, 2024: Project funding has been approved, contracts awarded, and construction schedules are being finalized. Click to view the press release as a PDF.

Construction-Schedules
Construction-Schedules

Construction Schedules:

Forcemain Construction Along State Line Beginning Spring 2025

​Schedule updated March 27, 2025

 

1. SPRING 2025

Crossing I435 and Indian Creek

2. SPRING/SUMMER 2025

Work near State Line Way Businesses

3. SUMMER 2025

89th Street to 93rd Street

4. SUMMER 2025

89th Street to W 100th Terrace

5. SUMMER 2025

93rd Street to 95th Street

6. SUMMER/FALL 2025

W 100th Terrace to 103rd Street

7. FALL 2025

95th Street Intersection

8. FALL 2025

95th Street to 98th Street & Reconnection at 103rd Street

9. WINTER 2025/SPRING 2026

Work in Leawood Park

​​

click on the map to view a larger PDF version

stateline-fullschedule-2025-0326.gif
Pump Station Construction Schedule Graphic - 8950 State Line Rd - Dykes Branch East

Pump Station - 8950 State Line Rd - Dykes Branch East

Pump Station Construction Schedule Graphic - 104th Street Station - 10346 State Line Road

Pump Station - 104th Street Station - 10346 State Line Road

Engagement

Project Engagement​

  • Engagement for the project has included joint and individual meetings for each of the pump stations.

  • Meeting materials and information for the previous engagement open houses/meetings can be found at the links in the "For More Information" box below. 

JCW Stateline Project Manager

Michael Cunningham

913-715-8545

stateline@jcwprogram.com

bottom of page