Detailed Monthly Schedule

Dec 2025

FORCEMAIN

  • Pavement restoration work will continue on 104th St to replace damaged pavement and the median near 8900 State Line Rd. 

  • Force main pipe will continue to be laid in Leawood Park west of Indian Creek.

  • Upcoming Traffic Impacts:

    • Lane closures of the two southbound lanes of State Line Rd will not occur until Spring 2026, for the remaining force main and pavement work in State Line Rd. ​

    • Lane closures of State Line Way, near 104th St, will occur during the first half of December for restoration of pavement in State Line Way and 104th Street.

PUMP STATIONS

  • Work will continue on gravity sewer along with additional shoring installed as needed at Dykes Branch East Pump Station (8950 State Line Rd.

  • Upcoming Traffic Impacts:  None anticipated for December.

Nov 2025

FORCEMAIN

  • Pavement restoration work will begin on 104th St to replace pavement and curb affected by the force main pipe and gravity pipe installations. 

  • Restoration of the creek embankment will continue, where the pipe installation work crossed Indian Creek, west of Leawoof Dog Park.

  • Restoration will continue in the medians between State Line Rd. and State Line Way.

  • Upcoming Traffic Impacts:

    • Lane closures of the two southbound lanes of State Line Rd will not occur until Spring 2026, for the remaining force main and pavement work in State Line Rd. ​

    • Lane closures of inside lanes of State Line Rd, near 89th St, may occur in November for restoration of roadway medians.

    • Intermittent lane closures of State Line Way, near 104th St, will continue to occur throughout November for pavement restoration.

PUMP STATIONS

  • Work will continue on gravity sewer along with additional shoring installed as needed at Dykes Branch East Pump Station (8950 State Line Rd.

  • Upcoming Traffic Impacts:  None anticipated for November.

Oct 2025

FORCEMAIN

  • Work will continue on the gravity sewer line in between O’Reilly’s and Fritz’s on State Line Way/104th St. 

  • Pipe work will continue west of Leawoof Park, for the force main pipe crossing Indian Creek.  
     

  • Upcoming Traffic Impacts:

    • Lane closures of the two southbound lanes of State Line Rd will not occur until Spring 2026, for the remaining force main and pavement work in State Line Rd. ​

    • Lane closures of inside lanes of State Line Rd, near 89th St, may occur in October for restoration of roadway medians.

    • Intermittent lane closures of State Line Way, near 104th St, will continue to occur throughout October.

PUMP STATIONS

  • Concrete will be poured for the walls of the diversion structure at 8950 State Line Rd.

  • Work will continue on gravity mains and other structures around the wet well structure at Dykes Branch East Pump Station.

  • Upcoming Traffic Impacts:  None anticipated for October.

Sept 2025

FORCEMAIN

  • Asphalt work will continue in the area south of 89th Street up to 92nd Street and from 97th Street to 100th Terrace. 

  • Work will begin on the gravity sewer line in between O’Reilly’s and Fritz’s on 104th St. 

  • The pedestrian/bike trail south of Indian Creek near 104th St. will be permanently restored. 

  • Pipe installation work will continue near 104th St, on State Line Way.  

  • Upcoming Traffic Impacts:

    • Lane closures of the two southbound lanes of State Line Rd will continue throughout September. 

      • The lane closures in September will continue to extend from approximately 89th St to the entrance of Rockhurst High School, and from approximately W 97th St to W 100th Terr. until pavement restoration is completed.

      • Followed by lane closures that will extend from approximately 92nd St to 95th St and from approximately W 100th Terr to 103rd St.

    • Traffic in State Line Rd will continue to be limited to one northbound lane and one southbound lane for the length and duration of the traffic control setup.  Only occasional traffic flagging is anticipated for deliveries of materials at the 8950 State Line Rd pump station site.

    • Intermittent lane closures of State Line Way, near 104th St, will continue to occur throughout September.

    • Temporary/intermittent road lane and driveway lane closures will be required on 104th Street, near O’Reilly’s, to install the new gravity sewer pipe through the O’Reilly’s property.  Access to all businesses on 104th St will be maintained.

PUMP STATIONS

  • Around the completed lower portion of the wet well structure backfill will begin as other associated subgrade structural work continues for the pump station at the 8950 State Line Rd. 

  • Upcoming Traffic Impacts:  None anticipated for September.

July - Aug 2025

FORCEMAIN

  • Pipe work will continue on State Line Rd. near 89th St. and at 97th St. to 100th Terr. working towards the south.

  • Stream crossing restoration at Indian Creek near 104th St.  

  • Force main pipe work will continue near 104th St. and tie into pipe previously laid under Indian Creek. 

  • After the gas line modifications are completed by Kansas Gas near 9000 State Line Rd. pavement restoration will begin.

  • Gravity pipe and force main pipe installation will continue near 104th St, and north to 103rd St.

  • Upcoming Traffic Impacts:

    • Lane closures of the two southbound lanes of State Line Rd will continue throughout August.  The lane closures in August will continue to extend from approximately 89th St to the entrance of Rockhurst High School, and from approximately W 97th St to W 100th Terr.   

    • Traffic in State Line Rd will continue to be limited to one northbound lane and one southbound lane for the length and duration of the traffic control setup.  Only occasional traffic flagging is anticipated for deliveries of materials at the 8950 State Line Rd pump station site.

    • Intermittent lane closures of State Line Way, near 104th St, will continue to occur throughout August.

PUMP STATIONS

  • Concrete work (rebar, form work, etc.) will continue for the subgrade walls of the poured-in-place concrete wet well for the pump station at the 8950 State Line Rd. 

  • Upcoming Traffic Impacts:  None anticipated for July/August.

June - July 2025

FORCEMAIN

  • Work will continue north of I-435 for the bored segment under the west bound ramp onto I-435.

  • Force main pipe installation work continues in State Line Rd. near 89th St, working towards the south.  Once force main pipe and pavement work are complete in this traffic control area, installation work will start on force main to the south of the current traffic control.

  • Force main pipe installation work will begin in State Line Rd from approximately W 97th St and towards the south to W 100th Terr.

  • Gravity pipe and force main pipe installation continues near 104th St, and north to 103rd St.  

  • Compete the pigging station near 104th St.

  • Begin work on a bored segment under 103rd St, west of State Line Rd.

  • Upcoming Traffic Impacts:

    • Lane closures of the two southbound lanes of State Line Rd will continue throughout July.  The lane closures in July will continue to extend from approximately 89th St to the entrance of Rockhurst High School, then later from approximately the entrance of Rockhurst High School to 95th St.  A second construction crew will begin work simultaneously, with lane closures extending from approximately W 97th St to W 100th Terr.

    • Traffic in State Line Rd will continue to be limited to one northbound lane and one southbound lane for the length and duration of the traffic control setup.  Only occasional traffic flagging is anticipated for deliveries of materials at the 8950 State Line Rd pump station site.

    • Also, intermittent lane closures of State Line Way, near 104th St, will continue to occur throughout July.

PUMP STATIONS

  • Continue excavation work at the pump station at 8900 State Line.

  • Begin form work and rebar work for the poured-in-place concrete wet well and other subgrade structures for the pump station.

  • Upcoming Traffic Impacts:  None anticipated for June/July.

May 2025

FORCEMAIN

  • Pipe installation from Indian Creek will continue, near 104th St, toward 103rd St to the north.  

  • Installation of  gravity sewer mains and manholes in the vicinity of State Line Way and 104th St.

  • There will be construction equipment near I-435 and State Line Road throughout May.

  • Temporary Trail Closure:

    • A new sewer force main pipe is being installed across/under Indian Creek (near the Indian Creek Trail south of Indian Creek, at State Line Rd and I-435) and will continue for approximately 2 to 3 weeks. 

    • Due to the difficulty in trying to maintain safe trails across an active construction site, the trail will not be reopened on nights and weekends.  Weather permitting, the trail is scheduled to reopen by June 13.​

    • We apologize for the inconvenience.  We are fully aware that the trail does not have a good alternative safe route for detouring and will make every effort to move as quickly as possible to get the construction work done safely and the trail restored.

  • Upcoming Traffic Impacts: Intermittent lane closures in State Line Way, near 104th Street are expected throughout May. 

  • We appreciate your patience as we work to safely complete the project. For the safety of the public and our workers, please follow all signage and safety guidelines.

PUMP STATIONS

  • Site piping and temporary bypass piping work will continue.  

  • Starting early May, the pump at 8950 State Line Rd will be bypassed in order to install temporary bypass manholes.  Bypass pumping is anticipated to occur for a maximum of 2 weeks.  

  • In mid-May, re-digging the wetwell will begin and installing excavation shoring.  Wetwell forming and concrete construction will begin at the end of May..

  • Upcoming Traffic Impacts:  None anticipated for May.

April 2025

FORCEMAIN  

Mobilization beginning under I-435​

  • The contractor working on the Forcemain portion of this project will begin mobilizing on April 2. Work will start under I-435.

  • Some impacts to traffic flow is expected. Please follow all signage and safety guidelines. 

  • There will be construction equipment near I-435 throughout April.

  • Upcoming Traffic Impacts: Southbound lane closures in State Line Rd, under the I-435 bridge, are anticipated to take place over a weekend in late April.

PUMP STATIONS

  • After getting an approved shoring and bypass plan, BRB will continue to excavate for the pump station structures at the Dykes Branch East Pump Station site. BRB will install temporary sewer around their shoring location, prior to installing the shoring.

  • Upcoming Traffic Impacts:  None anticipated for April.

March 2025

PUMP STATIONS

  • BRB Contractors and their subcontractors will be on site the week of March 3, 2025, to remove the three (3) sizable trees and small brush near the proposed Dykes Branch East Pump Station location.

  • BRB will also have equipment on site to begin constructing the chain link security fence around the construction site.

 

OUTREACH

Pump Station Project Kick-Off Open House Held - March 22, 2025

State Line Forcemain: A public notification postcard was sent to properties along Stateline about the start of the project.

For more detailed information go to the project page