top of page

Detailed Monthly Schedule

April 2025

FORCEMAIN  

Mobilization beginning under I-435​

  • The contractor working on the Forcemain portion of this project will begin mobilizing on April 2. Work will start under I-435.

  • Some impacts to traffic flow is expected. Please follow all signage and safety guidelines. 

  • There will be construction equipment near I-435 throughout April.

  • Upcoming Traffic Impacts: Southbound lane closures in State Line Rd, under the I-435 bridge, are anticipated to take place over a weekend in late April.

PUMP STATIONS

  • After getting an approved shoring and bypass plan, BRB will continue to excavate for the pump station structures at the Dykes Branch East Pump Station site. BRB will install temporary sewer around their shoring location, prior to installing the shoring.

  • Upcoming Traffic Impacts:  None anticipated for April.

March 2025

PUMP STATIONS

  • BRB Contractors and their subcontractors will be on site the week of March 3, 2025, to remove the three (3) sizable trees and small brush near the proposed Dykes Branch East Pump Station location.

  • BRB will also have equipment on site to begin constructing the chain link security fence around the construction site.

 

OUTREACH

Pump Station Project Kick-Off Open House Held - March 22, 2025

State Line Forcemain: A public notification postcard was sent to properties along Stateline about the start of the project.

For more detailed information go to the project page

bottom of page