top of page
top

Potential Future Projects

These projects are included in JCW’s Integrated Plan and Capital Improvements Plan. The final scope, schedule, and budget for the projects may vary and are subject to approval by the Johnson County Board of County Commissioners. 

Middle Basin WWTF Digestion and Solids Improvements

Douglas L Smith Middle Basin WWTF

Notice of Non-Mandatory One-on-One Meetings with Engineers and Contractors

Non-mandatory one-on-one meetings with Engineers and Contractors for the Middle Basin WWTF Digestion and Solids Improvements project were held June 8 – June 12. Attached is a PDF of the agenda for the meetings.

The Solids Treatment Conceptual Facility Plan for Middle Basin WWTF was completed by CDM Smith in October 2025. This Facility Plan identified multiple process areas that need improvement and prioritized them as High, Med-High, Medium, Med-Low and Low.

Total projected projects cost: $150 - $200 M.

The projects categorized as High, Med-High and Medium will be considered for the scope of this project and are summarized below:

 

  1. Digestor gas piping to flares

  2. New digested sludge storage tank 

  3. New support building for electrical gear and boiler room

  4. Convert secondary digester 2 to primary digester 

  5. Rehabilitate existing digesters 1, 3, & 4 

  6. Rehabilitate Digester Bldg.# 4 

  7. New solids processing forcemains 

  8. New two-story Dewatering Bldg. with three centrifuges and loading bay 

  9. Bldg.# 2 Modifications

  10. Centrate Equalization

  11. Site pavement and improvement

 

The facility plan also recommended collaborative delivery, preferably construction-manager-at-risk; this is pending Board review and approval.​

Procurement/Project Schedule:

Procurement project schedule for Middle Basin WWTF solids project.

Brush Creek Pump Station Improvements Project

Brush Creek Pump Station

Notice of Non-Mandatory One-on-One Meetings with Engineers and Contractors

Non-mandatory one-on-one meetings with Engineers and Contractors for the Brush Creek Pump Station Improvements Project were held June 8 – June 12.  A PDF of the agenda for the meetings is attached. 

The Brush Creek pump station preliminary engineering report (PER) was originally completed by HDR in August 2022 and updated in 2026 to incorporate the current wet weather forcemain plan, project cost estimate, and schedule.

Total projected project cost: $12 - $17 M.

The PER determined that the pump station will need to be replaced and will have:

  1. Influent screening

  2. Sized for dry weather and wet weather conditions

  3. Installation of dry weather submersible pumps

  4. Odor control

  5. Electrical and control room

  6. Site work and landscaping

 

The pump station is located by a city park in a residential area. Community outreach and close coordination with the City will be important.  

It is JCW’s desire to use collaborative delivery, preferably progressive design-build; this is pending Board review and approval.

Procurement/Project Schedule:

Procurement project schedule for Brush Creek Pump Station
bottom of page